LATEST UPDATE FOR RESIDENTS AT WOODWINDS

The Board of Directors would like to communicate with residents at this time regarding several projects that are coming up for this fall.  Due to time sensitivity, we are posting this information on the website so that residents may receive information in a timely manner.

Carport Roof Replacement

Per our reserve study,  the existing carport roof replacement was planned for 2018. Cutting Edge, Inc. will begin the replacement project on October 1st, 2018.  Estimated time of completion as well as start date may change depending on the weather.  Currently, the rake boards  are being replaced and the work being done now does not require vehicles to be moved and all this will be completed prior to starting the carport roof replacement.  We will update residents on any new information that may impact the community as  we receive them regarding this project.

Verizon FiOS

Verizon has recently informed us that they are ready to  begin the FiOs cable installation  project and will begin assessment in Woodwinds beginning the week of September 10th.  No details of the project schedule has been provided at this time.

Verizon contractors will be on the property and possibly on some balconies as they assess their installation project.  Please note that the workers will be wearing lime green shirts.

Final Asphalt Sealing

Residents will recall the major asphalt replacement project that took place in October of 2017.  As part of that project, final coat of sealant must be put on the asphalt.  No dates have been scheduled at this time but we do expect to complete this final project before the winter months.  Updates will be provided when available.